Master Bill of Materials

Consolidated reference — all categories · SSOT v3.7 · Audience: Owner, procurement, contractor

AC Acoustic Critical — cannot modify without written approval HP Hold Point — stop work, obtain sign-off

Phase Summary

Phase 1 — Construction Now
~$27,415
Walls, float floor, ceiling, doors, HVAC (V2 scalable — recommended)
Phase 2 — Equipment
~$14,962
AV gear, cameras, interfaces, studio monitors
Phase 3 — Software
~$9,808
DAW, plugins, subscriptions
V1 full build: ~$38,505 · V2 scalable (recommended): ~$27,415 · Owner gear already on hand saves ~$2,783

1. Acoustic Treatment

Panel order: 35 panels (order 38 with 10% buffer) installed → order 38 (10% buffer) AC
ItemSpecQty (installed)Qty (order)Notes
Absorption panelsRockwool RWA45 50mm · 1200×600mm · NRC 0.90353810% buffer AC
VO Live panelsAs above8Subset of 35
Control panelsAs above — first-reflection2Fixed position AC
Studio panelsAs above132 additional per ISM simulation verification
Editing panelsAs above4Required — RT60 fails without AC
Bass trapsRockwool RWA45 150mm · floor-to-ceiling14164 VO Live + 4 Control + 4 Studio + 2 Editing AC
QRD diffusersQuadratic Residue Diffuser442 Control rear + 2 Studio south

2. Doors & Windows

IDSizeSTCLocationSwingNotes
D190×220 cm50South wall x=434cmN into EditingAC
D290×220 cm45Buffer spine west faceW into Control
D380×220 cm45VO/Control partitionN into VO Live
D490×220 cm48Studio/Editing partition x=238.6cmAC
OW-180×50 cm50VO/Control partition · sill 100cm AFF5° tiltAC

3. Wall Materials

WallSTC LabThicknessKey materials
W1 North concrete65300mm concrete + RSIC-1 + hat channel + 50mm RW + 2×gyp
W2 NW diagonal65As W1 + RSIC-V clips
W3 East server6216 cm (16cm new build + 100mm pre-existing air gap to server room = 26cm total buildup)100mm air + 2×16mm gyp+GG + 70mm studs+RW + 2×16mm gyp+GG
W4 South rebuilt5015 cm2×12.5mm gyp + Green Glue + 100mm studs+RW + 2×12.5mm gyp + Green Glue
W5 Buffer spine5515 cm2×12.5mm gyp+GG + 100mm studs+RW + 2×12.5mm gyp+GG
W6 VO/Control5312 cm2×12.5mm gyp + Green Glue + 70mm studs+RW + 2×12.5mm gyp + Green Glue + OW-1 window cutout
W7 Studio/Editing4811 cm12.5mm gyp + GG + 12.5mm gyp + 70mm studs+RW70 + 12.5mm gyp AC

4. Float Floor

ItemSpecNotes
Isolation padsSylomer SR28 — full zone coverage
Plywood deck18mm T&G plywood · 2 layers · staggered joints
Perimeter gap25mm → closed-cell foam backing rod → Tremco sealantAC
Column box-out COL_W60×50cm · 10mm air gapAC
Column box-out COL_E60×55cm · 10mm air gapAC

5. HVAC — System Overview

UnitRoom servedLocationNC target
IDU-04VO Live — dedicatedNorth wallNC-12 max AC
IDU-03Control + Editing — sharedNorth wallNC-18 max
IDU-05Video Studio — dedicatedNorth wallNC-18 max
ODUOutdoor unit (Daikin VRF)South side

6. Electrical

ItemSpec
Sub-panel240V / 50Hz · 32A · TN-S star topology
Zone load3975W (52% utilization)
Conduit25mm EMT for Cat6A S/FTP
Data separation300mm min from power conduits
Standard outlets45cm AFF throughout
ST-GS outlet265cm AFF east wall Video Studio AC
Data panelsAV-01 to AV-04 · Cat6A S/FTP · TIA-568B

7. AV Equipment — Phase Summary

PhaseScopeBudget (V2)
Phase 1Construction + core AV~$27,415
Phase 2AV gear, cameras, interfaces~$14,962
Phase 3DAW, plugins, subscriptions~$9,808

See AV-EQUIPMENT.html for full room-by-room schedule.