Complete acoustic design package for the MediaVerse 4-room studio. MEP engineering required before construction procurement.
10-phase critical path with hold points. The master construction order.
LiveAcoustic panel placement maps for all 4 rooms. 35 panels (order 38 with 10% buffer) + 8 bass traps.
LiveEvery wall/floor/ceiling penetration sealed to maintain STC ratings.
LiveWall-to-floor, wall-to-ceiling, and wall-to-wall junction details.
LiveRT60 (Reverberation Time), NC (Noise Criteria), STC (Sound Transmission Class) verification procedures.
LiveAll hold points and QC gates across the 10 construction phases.
LiveVO Live ↔ Control Room stagebox chain plus independent Video Studio recording workflow with no fixed tie to Control.
LiveCRI (Color Rendering Index) ≥95 LED fixtures, DALI (Digital Addressable Lighting Interface) control, dimming.
LiveDamascus-sourced substitutes for imported acoustic materials.
LiveEgress routes, fire-rated assemblies, detection, suppression.
LiveAll 7 wall types (W1–W7) with layer-by-layer construction details.
LiveD1–D4 doors + OW-1 observation window. STC ratings, seals, hardware.
LiveFloat floor (Sylomer SR28 + T&G plywood) and acoustic ceiling systems.
LiveComplete material data sheets: Rockwool, Green Glue, gypsum, sealants.
Live6-surface interior views for all 4 rooms: 4 walls + ceiling + floor build-up. Interactive lightbox, zoomable drawings.
Live16 wall elevation drawings with acoustic treatment layout, MEP penetrations, electrical outlets, and dimension lines.
LiveSub-panel, AV circuits AV-01–AV-04, isolated ground, Cat6A routing.
LiveDuct sleeve details, fire stops, acoustic seals at every HVAC (Heating, Ventilation, and Air Conditioning) penetration.
LiveInteractive SVG floor plan with toggle layers.
LiveD2/D3 acoustic airlock between VO Live and Control Room. Clearances, sequencing, seal requirements.
LiveMonitor positioning, mic placement, camera throw, and equipment layout for all rooms.
LiveCustom L-shaped Control Room desk. Steel frame, birch plywood, SSL UF8 recess. Full build spec.
LiveAbsorption panels (38), bass traps (8), and QRD diffusers (4). Materials, tools, mounting.
LiveBuild acoustic doors STC 40/45/48. Leaf construction, frame specs, seal types.
LiveRoom-by-room floor, wall, and ceiling finishes. Paint, vinyl, carpet, skirting specs.
LiveDoor hardware for D1-D4. Hinges, seals, closers, drop seals, maintenance schedule.
LiveD1–D4 cross-sections, threshold details, frame rebates, seals, and hardware coordination.
LiveOne contractor-scale cross-section for each wall type W1–W7 with total thickness and layer labels.
LiveSlab-to-finish section, Sylomer pad plan, and perimeter isolation joint detail.
LiveOW-1 triple-pane cross-sections, 5° tilt, sill level, and 7-step installation sequence.
LiveConduit, cable, duct, and pipe sealing details with acoustic / fire coordination callouts.
LiveRoom-by-room pad layouts, perimeter gap lines, column keep-outs, and order quantities.
Live25 mm isolation gap details, column clearances, and wrong-vs-right skirting conditions.
LiveWall-to-floor, partition head, concrete ceiling edge, corner junction, and column isolation details.
LiveFrench cleats, anchor isolation, bass trap corner mounting, and QRD diffuser installation heights.
LiveSB-01 face plate, sealed W6 conduit penetration, local Studio floor-box services, and Control rack landing.
LiveRun A, B, B1, B2, and C silencer sections with installation spacing and IDU-03 crossover warning.
LiveAcoustic ceiling section, perimeter wall angle, plenum barriers, and Video Studio T-grid layout.
LiveLegacy contractor drawing package covering floor plan, sections, column isolation, door assembly, and observation window references.
Live10-phase flowchart with swim lanes, durations, trade ownership, and formal hold points before downstream work.
LiveRACI allocation for procurement, installation, consultant review, and commissioning responsibilities.
LiveDamascus-market substitution table with performance deltas, adjustments, and must-import warnings.
LiveDamping mechanism, blob pattern, cure timing, common mistakes, and wall-by-wall applicability.
LiveRT60, NC, and field D'nT,w test layouts with acceptance criteria and critical pass notes.
LivePlan, elevation, and cable-management references for the Control Room joinery package.
LivePrintable phase-by-phase checklist with hold-point summary and signature lines for inspection walks.
LiveSimplified floor-plan overlay of audio, power, data, video, and tally routes with acoustic penetration callouts.
Live| Item | Requirement | Marker |
|---|---|---|
| Float floor perimeter | 25 mm gap → backing rod → Tremco sealant | [AC] |
| Structural columns | 10 mm air gap from ALL framing — COL_W (60×50 cm) & COL_E (60×55 cm) | [AC] |
| Ceiling AFF (Above Finished Floor) | Exactly 275 cm everywhere. Never 315, 290, or 270. | [AC] |
| Editing Suite panels | 4 panels REQUIRED — without them RT60 (Reverberation Time) = 0.42 s, fails NC-25 target | [AC] |
| HVAC duct routing | Buffer spine ONLY — no duct penetrations through acoustic walls | [AC] |
| Green screen outlet ST-GS | Exactly 265 cm AFF, east wall, Video Studio | [AC] |