Complete acoustic design package for the MediaVerse 4-room studio. MEP engineering required before construction procurement.

All Construction Documents

Installation Sequence

10-phase critical path with hold points. The master construction order.

Live

Treatment Layouts

Acoustic panel placement maps for all 4 rooms. 35 panels (order 38 with 10% buffer) + 8 bass traps.

Live

Penetration Sealing

Every wall/floor/ceiling penetration sealed to maintain STC ratings.

Live

Junction Isolation

Wall-to-floor, wall-to-ceiling, and wall-to-wall junction details.

Live

Testing & Commissioning

RT60 (Reverberation Time), NC (Noise Criteria), STC (Sound Transmission Class) verification procedures.

Live

Inspection Checkpoints

All hold points and QC gates across the 10 construction phases.

Live

Studio Signal Infrastructure

VO Live ↔ Control Room stagebox chain plus independent Video Studio recording workflow with no fixed tie to Control.

Live

Lighting Infrastructure

CRI (Color Rendering Index) ≥95 LED fixtures, DALI (Digital Addressable Lighting Interface) control, dimming.

Live

Local Alternatives

Damascus-sourced substitutes for imported acoustic materials.

Live

Fire & Life Safety

Egress routes, fire-rated assemblies, detection, suppression.

Live

Wall Sections

All 7 wall types (W1–W7) with layer-by-layer construction details.

Live

Door & Window Details

D1–D4 doors + OW-1 observation window. STC ratings, seals, hardware.

Live

Floor & Ceiling

Float floor (Sylomer SR28 + T&G plywood) and acoustic ceiling systems.

Live

Material Specifications

Complete material data sheets: Rockwool, Green Glue, gypsum, sealants.

Live

Comprehensive Elevations

6-surface interior views for all 4 rooms: 4 walls + ceiling + floor build-up. Interactive lightbox, zoomable drawings.

Live

Wall Elevations

16 wall elevation drawings with acoustic treatment layout, MEP penetrations, electrical outlets, and dimension lines.

Live

Electrical

Sub-panel, AV circuits AV-01–AV-04, isolated ground, Cat6A routing.

Live

HVAC Penetrations

Duct sleeve details, fire stops, acoustic seals at every HVAC (Heating, Ventilation, and Air Conditioning) penetration.

Live

Master Drawing

Interactive SVG floor plan with toggle layers.

Live

Sound Lock Detail

D2/D3 acoustic airlock between VO Live and Control Room. Clearances, sequencing, seal requirements.

Live

Equipment Placement

Monitor positioning, mic placement, camera throw, and equipment layout for all rooms.

Live

Desk Fabrication

Custom L-shaped Control Room desk. Steel frame, birch plywood, SSL UF8 recess. Full build spec.

Live

Panel Fabrication

Absorption panels (38), bass traps (8), and QRD diffusers (4). Materials, tools, mounting.

Live

Door Fabrication

Build acoustic doors STC 40/45/48. Leaf construction, frame specs, seal types.

Live

Finish Schedule

Room-by-room floor, wall, and ceiling finishes. Paint, vinyl, carpet, skirting specs.

Live

Hardware Schedule

Door hardware for D1-D4. Hinges, seals, closers, drop seals, maintenance schedule.

Live

Contractor Detail Drawings

Acoustic Door Details

D1–D4 cross-sections, threshold details, frame rebates, seals, and hardware coordination.

Live

Wall Cross-Sections

One contractor-scale cross-section for each wall type W1–W7 with total thickness and layer labels.

Live

Float Floor Build-Up

Slab-to-finish section, Sylomer pad plan, and perimeter isolation joint detail.

Live

Observation Window Detail

OW-1 triple-pane cross-sections, 5° tilt, sill level, and 7-step installation sequence.

Live

Penetration Details

Conduit, cable, duct, and pipe sealing details with acoustic / fire coordination callouts.

Live

Sylomer Layout Plans

Room-by-room pad layouts, perimeter gap lines, column keep-outs, and order quantities.

Live

Perimeter Gap Detail

25 mm isolation gap details, column clearances, and wrong-vs-right skirting conditions.

Live

Acoustic Junction Details

Wall-to-floor, partition head, concrete ceiling edge, corner junction, and column isolation details.

Live

Panel Installation

French cleats, anchor isolation, bass trap corner mounting, and QRD diffuser installation heights.

Live

Stagebox Detail

SB-01 face plate, sealed W6 conduit penetration, local Studio floor-box services, and Control rack landing.

Live

HVAC Silencer Detail

Run A, B, B1, B2, and C silencer sections with installation spacing and IDU-03 crossover warning.

Live

Ceiling Detail

Acoustic ceiling section, perimeter wall angle, plenum barriers, and Video Studio T-grid layout.

Live

Project Reference Documents

Contractor Drawings

Legacy contractor drawing package covering floor plan, sections, column isolation, door assembly, and observation window references.

Live

Construction Trade Sequence

10-phase flowchart with swim lanes, durations, trade ownership, and formal hold points before downstream work.

Live

Responsibility Matrix

RACI allocation for procurement, installation, consultant review, and commissioning responsibilities.

Live

Material Substitution Guide

Damascus-market substitution table with performance deltas, adjustments, and must-import warnings.

Live

Green Glue Guide

Damping mechanism, blob pattern, cure timing, common mistakes, and wall-by-wall applicability.

Live

Commissioning Setup

RT60, NC, and field D'nT,w test layouts with acceptance criteria and critical pass notes.

Live

Control Room Desk Layout

Plan, elevation, and cable-management references for the Control Room joinery package.

Live

Site Inspection Checklist

Printable phase-by-phase checklist with hold-point summary and signature lines for inspection walks.

Live

Cable Routing Plan

Simplified floor-plan overlay of audio, power, data, video, and tally routes with acoustic penetration callouts.

Live

Key Acoustic Reminders

ItemRequirementMarker
Float floor perimeter25 mm gap → backing rod → Tremco sealant[AC]
Structural columns10 mm air gap from ALL framing — COL_W (60×50 cm) & COL_E (60×55 cm)[AC]
Ceiling AFF (Above Finished Floor)Exactly 275 cm everywhere. Never 315, 290, or 270.[AC]
Editing Suite panels4 panels REQUIRED — without them RT60 (Reverberation Time) = 0.42 s, fails NC-25 target[AC]
HVAC duct routingBuffer spine ONLY — no duct penetrations through acoustic walls[AC]
Green screen outlet ST-GSExactly 265 cm AFF, east wall, Video Studio[AC]
[AC] Acoustic Critical — Cannot be modified without written approval from the acoustic consultant.    [HP] Hold Point — Stop work and obtain sign-off before proceeding to next phase.    [DEC] Decorative — Can be customized within the stated constraints (color, texture, finish).