Site Inspection Checklist

Printable inspection sheet for trade supervisors and acoustic sign-off walks. Each phase includes a dedicated signature line so the responsible inspector can record acceptance before downstream works proceed.

Format
Printable
Hold Points
HP-1 / 2 / 3 / 10
Critical Tags
[AC] + [HP]
Use
Site inspections

Hold Points Summary

Must Sign Off

HP-1

Structural sign-off before floor works.

HP-2

Penetration sealing inspection before ceiling.

HP-3

Perimeter gap inspection before floor finish.

HP-10

Commissioning certificate before handover.

Phase Checklists

Inspector Signatures Per Phase

Phase 1 — Pre-Construction

  • ☐ Structural slab capacity confirmed ≥ 45 kg/m²
  • ☐ All penetration sleeve positions marked
  • ☐ MEP contractor briefed on annular gap requirement
  • ☐ Green Glue delivery confirmed before wall works
  • ☐ Sylomer SR28 delivery confirmed
Inspector: ____________________ Date: ____________________

Phase 2 — Wall Framing

  • ☐ W3 / W4 / W5 / W6 / W7 stud positions verified
  • ☐ No stud touching concrete on resilient clip walls
  • ☐ RSIC-1 clips at 600 mm spacing
  • ☐ Hat channel seated in clips
  • ☐ No direct metal-to-metal contact through assembly
Inspector: ____________________ Date: ____________________

Phase 3 — Gypsum and Green Glue

  • ☐ First layer screwed to hat channel
  • ☐ GG applied to correct walls: W3, W4, W5, W7
  • ☐ GG blob pattern verified (not spread, not at edges)
  • ☐ Second layer laminated within 15 minutes
  • ☐ All joints staggered minimum 400 mm
Inspector: ____________________ Date: ____________________

Phase 4 — Penetration Sealing [HP]

  • ☐ All conduit penetrations sealed Tremco both sides
  • ☐ All duct penetrations with fire collar both sides
  • ☐ Annular gaps only — no solid fill
  • ☐ Sign-off by acoustic consultant
Inspector: ____________________ Date: ____________________

Phase 5 — Float Floor [HP]

  • ☐ Sylomer pads at 400 mm grid
  • ☐ Bottom T&G plywood installed
  • ☐ Top T&G plywood staggered joints 400 mm offset
  • ☐ 25 mm perimeter gap maintained all around
  • ☐ Backing rod installed in gap
  • ☐ Tremco sealant applied over backing rod
  • ☐ Gap inspection sign-off before finish
Inspector: ____________________ Date: ____________________

Phase 6 — Ceiling

  • ☐ T-grid at exactly 275 cm AFF all rooms
  • ☐ 100 mm Rockwool ProRox above all tiles
  • ☐ Plenum barriers at all partition intersections
  • ☐ 5 mm gap between tile and wall (no caulking)
Inspector: ____________________ Date: ____________________

Phase 7 — MEP Fit-Out

  • ☐ Silencers installed per run lengths
  • ☐ HVAC connections complete
  • ☐ IDU-03 crossover silencer verified [HP]
  • ☐ Electrical outlets at correct heights
  • ☐ Data points tested for continuity
Inspector: ____________________ Date: ____________________

Phase 8 — Treatment

  • ☐ All absorption panels installed per layout
  • ☐ 50 mm gap from ceiling and floor
  • ☐ Bass traps in all room corners per spec
  • ☐ 50 mm air gap behind bass traps
  • ☐ QRD diffusers at Control south and Studio south
  • ☐ Observation window OW-1 tilted 5° verified
Inspector: ____________________ Date: ____________________

Phase 9 — Doors

  • ☐ D1 STC 50 hung and drop seal operational
  • ☐ D2 STC 45 hung and drop seal operational
  • ☐ D3 STC 45 hung and drop seal operational
  • ☐ D4 STC 48 hung and drop seal operational
  • ☐ All doors: compression seal contact verified
  • ☐ All doors: acoustic mortise lock operational
Inspector: ____________________ Date: ____________________

Phase 10 — Commissioning [HP]

  • ☐ RT60 test completed all rooms
  • ☐ NC test completed with HVAC running
  • ☐ 4 panels installed in Editing Suite [AC]
  • ☐ All results meet pass criteria
  • ☐ Acoustic consultant certificate issued
  • ☐ Client handover complete
Inspector: ____________________ Date: ____________________