SSOT v3.7 · Contractor Detail Drawing · Acoustic Design Basis
Observation Window OW-1 Installation Detail
Triple-pane observation window in the W6 partition between Control Room and VO Live. This detail shows the 170 mm steel frame, 5° tilt, sill level, and staged glazing installation sequence.
Opening
80 × 50 cm
Rating
STC 50
Frame Depth
170 mm
Tilt
5° [AC]
Drawing 1 — Horizontal Cross-Section
Frame depth 170 mmHorizontal cut through the W6 partition and observation frame. Three 6 mm panes are separated by two 50 mm air gaps with differing pane positions to avoid parallel reflective paths.
Drawing 2 — Vertical Cross-Section
Sill 100 cm AFF · 5° tiltVertical section through the OW-1 opening showing sill level, frame embedment into W6, and the 5° glazing tilt required to avoid flutter reflections between rooms.
Drawing 3 — Installation Sequence
7-step site sequenceInstall the frame first, then stage panes and seals from the larger air-gap side to the smaller air-gap side. Maintain clean seals at every interface.
| Step | Action |
|---|---|
| 1 | Form the W6 opening and verify sill elevation at 100 cm AFF. |
| 2 | Set the powder-coated steel frame and rebated reveal. |
| 3 | Shim frame plumb, lock to studs, and apply neoprene isolation strip. |
| 4 | Install first 6 mm pane with primary spacer. |
| 5 | Install second pane with 50 mm air gap and staggered depth. |
| 6 | Install third pane and final compression beads. |
| 7 | Seal frame-to-wall perimeter and inspect sightline / tilt before handover [AC]. |